Petrogas Burrows Service Station, Port Tennant, Swansea

Petrogas Abertawe Service Station, Fforestfach, Swansea
February 17, 2015
Petrogas Drayton Service Station, Norwich
February 17, 2015

We attended this forecourt site in Swansea to carry out a full survey as the canopy was leaking in multiple areas.  The canopy was found to have a very corroded roof and gutters with years of repair and patch work, there was also damage to the MM10 profile aluminium underlining sheets.

DSCF4911                        DSCF4902

 

We returned to site to supply, deliver and install complete new gutter runs with new outlets and spigots, we also removed the whole of the existing roof and replaced with 0.7mm galvanised roof sheets, secured by Tek screws, foam fillers to the eaves and a new ridge cap to the length of the canopy.
To the underside of the main canopy section we removed the underlining completely and replaced with new MM10 aluminium underlining sheets finished white to one side and fixed to the existing support grid.

DSCF5038                       DSCF5044

 

Whilst on site we also supplied, delivered and installed a bottom fascia trim to three elevations of the canopy, together with a complete wrap around fascia to the rear elevation adjacent to the car wash housing.

DSCF5055